0
Minutes downtime
Reversible cutover with full rollback
100%
Workloads migrated
60 VMs including SAP and MES
35%
Infrastructure cost saved
vs. running on-premise refresh
The challenge
Atlas's on-premise data center was reaching end-of-life. Their SAP and MES workloads ran on 60 VMs with hard business constraints: zero downtime, strict change windows and a small IT team.
How we fixed it
We built a landing zone in Azure, migrated workloads with Azure Migrate using continuous replication, automated the cutover with runbooks, and ran a full parallel run for two weeks before the final switch.
AzureVMwareMigration